CNTT Elbrus release planning (for reference)
Proposed milestones
Milestone | Description | Software Tasks / Criteria | Specification Tasks / Criteria (adapted from Elbrus release) | Delta | Notes |
---|
M0 | Start of release | None | None |
|
|
M1 | Release planning | - RM & RA versions selected
- Features selected for implementation from specifications
- RC & RI effort scoped with owners identified
- Major upstream component versions determined (e.g., OpenStack, Kubernetes)
- Project release plans submitted
- Release schedule approved
| - Create the high level scope
- Create initial list of Github issues, starting with issues that match the scope (originally M2 for Elbrus)
- Release schedule approved
| M0+4w |
|
M2 | Contents Freeze | - Initial RC(s) ready for RI implementation
- Jira issues assigned to release
| - Update content via PRs, matching to issues created
| M0+14w |
|
M3 | RC Validation Testing | - RC validation testing completed
- High priority Jira issues resolved
- Preliminary documentation completed
| - Find typo's, correct with PRs
| M0 + 18w |
|
M4 | RI Validation Testing | - RI validation testing completed
- High priority Jira issues resolved
|
| M0+22w |
|
M5 | Release Readiness | - Final documentation completed
- RI cookbook completed
- Manifest completed
- Remaining Jira issues assigned to the release closed or pushed to next release
- Release artifacts prepared
- Standalone project testing completed
- Marketing highlights page completed
| - Select release content (originally M4 for Elbrus)
| M0+25w |
|
M6 | Release | - Release artifacts available for distribution
- Standalone project self-release completed
| - Package the release, setup tag at ReadTheDocs
| M0+26w |
|
Schedule Proposal for June Release (compressed to 16 w)
Milestone | Date | Notes |
---|
M0 | |
|
M1 | |
|
M2 | |
|
M3 | |
|
M4 | |
|
M5 | |
|
M6 | |
|
Notes
Attendees: David, Al, Jim, Trevor
- Plan for set of milestones for software development, since we have agreed that specifications and software will use different cadences.