FOR REFERENCE ONLY:  CNTT Elbrus release planning

MilestoneDescriptionTasks / CriteriaDeltaNotes
M0Start of releaseNone

M1Release planning
  • RM & RA versions selected 
  • Features selected for implementation from specifications
  • Major upstream component versions determined
  • Project release plans submitted
  • Release schedule approved 
M0+4w
M2Code Freeze
  • Initial RC(s) ready for RI implementation
  • Jira issues assigned to release
M0+14w
M3RC Validation Testing
  • RC validation testing completed
  • High priority Jira issues resolved
  • Preliminary documentation completed
M0 + 18w
M4RI Validation Testing
  • RI validation testing completed
  • High priority Jira issues resolved
M0+22w
M5Release Readiness
  • Final documentation completed
  • RI cookbook completed
  • Manifest completed
  • Remaining Jira issues assigned to the release closed or pushed to next release
  • Release artifacts prepared
  • Standalone project testing completed
  • Marketing highlights page completed
M0+25w
M6Release
  • Release artifacts available for distribution 
  • Standalone project self-release completed
M0+26w

Notes

Attendees:  David, Al, Jim, Trevor

  • Plan for set of milestones for software development, since we have agreed that specifications and software will use different cadences.