03/06/18 --
Milestone 5 complete
Scenario deployment passed
Functest failing
MS6 03/16/18
Test case implementation completed.
Preliminary documentation completed.
Complete documentation compliance table for MS6.
First day that projects may request creation of the stable branch for their project.
APEX
Functests failing
Virtual deploy -- RDT, Hugepages… Should we skip during virtual deploy?
APEX deployment help -- Aaron has a test setup running and can answer questions.
Collectd
PRs
pmu plugin / pmu core -- Reviewer comments -- 03/06/2018
ovs link status -- Is this still relevant?
AMQP1 -- Needs review
Connectivity Event -- Reviews in progress
Process Event -- Reviews in progress
System Event -- Reviews in progress
DMA project would like to have another meeting (possibly at ONS)
Did you get your feedback to Alok? I know I didn’t yet :(.
Want to get comments by the 15th
Produce a spec update by end of March
Have a weekly update
VES Update
VES Project into ETSI
Parts of the project, metric / event definitions, transport
Pair things down to what’s important
10’s of collectors at present
VES mobile edge platforms
CAdvisor plugin for collectd?
Maybe try in the Barometer container?
02/27/18 --
Milestone 5 approaching
Thanks for the help on Apex and Barometer
Tracked down issue with deploy
Standards Update
VES Update
Barometer containers to be part of RDO release
Team to work on building Kolla containers
AMQP1.0 container being built
02/20/18 --
Collectd on Cumulus
Open Compute / Networking
Standards Updates?
VES Updates?
Development
Apex scenarios are currently failing
Ansible script reviews in progress
MS5 approaching
Barometer next?
02/13/18 --
Should Barometer Graduate? (https://www.opnfv.org/software/technical-project-governance/project-lifecycle)
Are we a part of enough scenarios (another installer)?
Would be a good recognition of the work done by Barometer
Have had good recognition at shows (OpenStack Summit, OPNFV, etc)
Bryan would be supportive of applying for graduation
No definitive answer, but positive reception
Standards Update (Al)
Meeting with IFA working group completed work on all measurement content. Al provided an edit / rewrite of the document and resubmitted.
Discussion of GAPs in Baromter
VES Update
Bryan working on Barometer Kubernetes scenario. Should be ready soon. Barometer as DaemonSet
Conversion of VES to gRPC in the testing phase.
Development Update
Ansible scripts submitted to Gerrit
Clarification that plugins not in collectd yet should still make it into Barometer / Fraser
(MS5) Scenario integration and feature freeze -- 03/02/18
Good discussion on “What’s next for Barometer”
Scope expansion -- Should Barometer move beyond metrics / events to policy
Scope continuation into container space --
OPNFV Barometer people going to ONS in March
Aaron
Al
Bryan
??