MilestoneDescriptionSoftware Tasks / CriteriaSpecification Tasks / Criteria (adapted from Elbrus release)DeltaNotes
M0Start of releaseNoneNone

M1Release planning
  • Major upstream component versions determined (e.g., OpenStack, Kubernetes)
    • RM & RA versions selected 
    • Features selected for implementation from specifications
    • RC & RI effort scoped with owners identified
    Major upstream component versions determined (e.g., OpenStack, Kubernetes)
  • Project release plans submitted
  • Release schedule approved 
  • Create the high level scope
  • Create initial list of Github issues, starting with issues that match the scope (originally M2 for Elbrus)
  • Release schedule approved 
M0+4w
M2Contents Freeze
  • Initial RC(s) ready for RI implementation
  • Jira issues assigned to release
  • Update content via PRs, matching to issues created 
M0+14w
M3RC Validation Testing
  • RC validation testing completed
  • High priority Jira issues resolved
  • Preliminary documentation completed
  • Find typo's, correct with PRs
M0 + 18w
M4RI Validation Testing
  • RI validation testing completed
  • High priority Jira issues resolved

M0+22w
M5Release Readiness
  • Final documentation completed
  • RI cookbook completed
  • Manifest completed
  • Remaining Jira issues assigned to the release closed or pushed to next release
  • Release artifacts prepared
  • Standalone project testing completed
  • Marketing highlights page completed
  • Select release content (originally M4 for Elbrus)
M0+25w
M6Release
  • Release artifacts available for distribution 
  • Standalone project self-release completed
  • Package the release, setup tag at ReadTheDocs
M0+26w

...