Anuket Project

You are viewing an old version of this page. View the current version.

Compare with Current View Page History

Version 1 Next »

M5

  • Final documentation completed
  • RI cookbook completed
  • Remaining Jira issues assigned to the release closed or pushed to next release
  • Prepare release artifacts
    • Tag the version of artifacts to be released
      • releng job updated to use release branch instead of master
    • Release manager collects artifact references from PTLs and communicates those to releng
    • Releng moves artifacts to hosting location and provides URLs to RM
    • RM verifies URLs
    • RM provides confirmed URL list to website manager (aka Brandon) for publication on the website
  • Standalone project testing completed
  • Release content finalized
  • Creation and submission of marketing highlights
  • Finalize version numbering for RM, RA1, RA2
  • Traceability matrix updated

Notes on M5

M4-S

  • Proofreading completed.
  • No labels