Agenda:

      • Agenda and Minutes
        • Agenda bashing
          • Time of the RM meeting:  Meeting agreed to have alternating times: at 14:00 UTC and 21:00 UTC (every other week): Walter to change / send invites and info
          • Chapter 3 structure: Hardware acceleration and SFC; where to put them: leave theses sections as separate  
          • Profile and flavors: PR#2312 (approved and merged), PR#2320, PR#2268
          • Use case review: No PR raised so far.
          • Security: Issues 2313 - 2318 raised, PR#2343 under review
          • Time synchronization: PR# 2347 under review (sec 3.4 and 3.9)
          • Networking semantics (based on Per's presentation): current contents fits into RA-2 rather than RM. What do we need in RM? Per to raise a PR for 3.5.2
            • Collaboration with GSMA OPG: workload profile flavours to be developed within RM (similarly like infrastructure / node profiles); Issue #2354;  a work page in WiIki for collaboration (OBSOLETE) Anuket + OPG Working Space
          • Update on joint XGVELA / Anuket PaaS Survey: Pankaj Goyal
          • Update on Hardware Acceleration activities: Petar Torre
          • Update on Networking Semantics activities: Per Andersson To create Issue(s) and PRs
          • Update on Security activities: Karine Sevilla PR#2343 for the team review
          • Issue#2352 (https://github.com/cntt-n/CNTT/issues/2352); modify CNTT Technical Policies and Transition Plan regarding the addition of acceleration technologies in RM: Karine Sevilla

          • Review and update on the Kali RM Issues and related PRsSFC: PR#2319 ready to merge
          • Global update to RM doc from CNTT to Anuket

    Anuket Kali release milestones: 

    M0Start of release

     


    M1Release planning

     


    M2Scope Freeze

     


    M3Content Freeze

     


    M4Proofreading

     


    M5Release Readiness

     


    M6Release

     


    Actions:

    1. Pankaj Goyal to send message to the RM team for review when the survey is ready
    2.  Beth Cohen to contact Karine Sevilla regarding storage work for the Kali release

    ...