  • Nile:
    • Kickoff: August 2
    • Release definition: August 16
    • Release scope (M2): September 20
    • Content freeze (M4): October November 22
    • Proofreading (M4S): December 6
    • Sign off (M5): December 13
  • Planning Dashboard for Nile
  • Yoga: RA1 will upgraded if Functest is ready. If it is not, the upgrade will be postponed to the following release.

GSMA NG.133 v2 and

...

OITF#13 outcomes

  • NG.133 CR 1002 modified after the meeting with Javier Sendin. New A new version was uploaded the 29th of October on GSMA IC2 website for review.
  • An editorial version will be needed, there are still some issues with table captions( blank lines).
  • OITF#13 meeting on 3rd of October, outcomes:
    • Approvals by OITF group for NG.126 v3 and NG. 133 v2. The next step will be the approval by NG16 on Friday. Some reviews should be expected.
    • RA2: decision to create to a new PRD. Comment:  the content is not answering the need at this point, it should be improved with technical choices.
    • OITF future:  the creation of a sub-group will be proposed by Walter and Pankaj 

Review of ongoing issues and PRs

  • PR 3211: editorial, "must" in Capital Letters, it is relevant for requirements only, not in all the sentences. Cedric will change the PR.

Next meetings

2022-10-10: next meeting

...