Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

Revision: r4r3

Image RemovedImage Added

Change Log

DateRevisionEvent / ChangeMilestones Affected
NotesApr 19r4TSC approved revised scheduleM3, M4, M4-SM3 slips two weeks.  M4 and M4-S slip one week. Signoff stays the same.Mar 29r3TSC approved change to release process

M3, M4,

M4-S

  • New milestone added (M4-S)
  • "Specification created" task moved from M3 to M4
  • "Proofreading" task moved from M4 to M4-S
  • Dates for existing milestones unchanged
Feb 1r2TSC approved M1M1Dec 15r2Updated events, and Lakelse Sign OffNone
08/09/22r3TSC approved moving M2 one week to Sept 13 to avoid conflict with the Labor Day holiday in the U.S.M2
08/02/22r2Corrected copy-and-paste error on schedule and added CNCF Telecom Day.None
06/14/22r1The TSC approved the schedule.All
06/14/22r1

Second draft.

Note: M5 and Sign Off are now merged into a single milestone.  This was discussed at the June 7 TSC meeting.

All
05/10/22
Dec 14r1Approved by the TSCallDec 14r1second draftM0, M1Moved kickoff to Jan 11 and M1 to Feb 1Nov 1

Initial draftAll