Milestone | Description | Delta in weeks | Date |
---|---|---|---|
M0 | Start of release | 0 |
|
M1 | Release Definition | M0 + 2w | Nov 2023 |
M2 | Scope Freeze | M1 + 2w |
|
M3 | RC Validation Testing |
| |
M4 | RI Validation Testing / Content Freeze | M3 + 5w | 09 Apr |
M4-S | Proofreading | M4 + 1w | 16 Apr |
M5 | Release Readiness | M4-S + 4w | 14 May |
Change Log
Date | Revision | Event / Change | Milestones Affected | ||||
---|---|---|---|---|---|---|---|
| 1 | Creation of schedule | M0, M1, M2, M3, M4, M4-S, M5 | ||||
| 2 | Update based on the assumption that Orinoco will be signed off on | M0, M1, M2, M3, M4, M4-S, M5 | ||||
| 3 | Update based on the assumption that Orinoco will be signed off on | M0, M1, M2, M3, M4, M4-S, M5 | ||||
| 4 | Approval of M1, skipping of M2 | M1, M2 | ||||
| 5 | Skipping M3 as there are no implementation projects. | M3 | ||||
template page | |||||||
| 2 | Move M2 to | M2 |
| 6 | Moving M4 to and delay all following milestones with 2 weeks | M4, M4-S, M5 |