M5
Final documentation completed
RI cookbook completed
Remaining Jira issues assigned to the release closed or pushed to next release
Prepare release artifacts
Tag the version of artifacts to be released
releng job updated to use release branch instead of master
Release manager collects artifact references from PTLs and communicates those to releng
Releng moves artifacts to hosting location and provides URLs to RM
RM verifies URLs
RM provides confirmed URL list to website manager (aka Brandon) for publication on the website
Standalone project testing completed
Release content finalized
Creation and submission of marketing highlights
Finalize version numbering for RM, RA1, RA2
Traceability matrix updated
Notes on M5
M4-S
Proofreading completed.
Notes on M4-S
New milestone approved by
TSC agreement Mar 29, 2022
Proofreading completed moved from M4
M4
RI validation testing completed.
The lead for each RI presents the validation plan and results to the TSC.
High priority Jira issues resolved (closed or assigned to future release)
Specification content created matching high level issues (M2) (Note: moved from M3, per
TSC agreement Mar 29, 2022
)
Workstream leads review PR status with TSC
PRs indicated as closed on the specification dashboard
Notes on M4
Specification content created - moved from M3 per
TSC agreement Mar 29, 2022
M3
RC2 -
RC workstream lead confirms successful completion of validation test plan
(statement in TSC meeting or email to TSC list)
High priority Jira issues resolved (closed or assigned to future release)
Preliminary documentation completed (confirmed by DOCs team)
RI2 development completed (confirmed by workstream lead)
Notes on M3
M2
RC2 - ready to begin validation testing (statement in TSC meeting or email to TSC list)
RC2 - coverage of RA specified
Jira issues assigned to release for each participating project (should reflect work described in project release plan)
High level issues identified by specification team and appear on dashboard.
Notes on M2
M1
RC Workstream lead(s) recommend
RM and RA versions
to the TSC for use in the release
RI workstream lead(s) recommend
RM and RA versions
to the TSC for use in the release
RC
validation plan
created or updated
RI
validation
plan created or updated
Release string "Moselle Release" created in Jira
Release string "Moselle Release" created in GitHub
Release milestone dates added to GitHub
PTLs
submit project-level release plans
Workstream leads complete
specification planning template
for release
RC workstream leads propose
plan for RC development
(based on an updated RA)
Notes on M1